Pantheon Elysee 08/09/2019 Monitoring Report

pantheon-impr-18-9-19

Following is the RERA, Government of Dubai Independent Progress Monitoring Report for Pantheon Elysee.

Inspection Date: 08/09/2019

Pantheon Elysee Project Details

Land Number: 151
Project Number: 1988
Project Name: PANTHEON ELYSEE
Project Location: Al Barsha South Fourth
Project Percentage: 31.31%
Real Estate Developer Name: PANTHEON REAL ESTATE DEVELOPMENT
Developer Number: 1173
Master Developer Name: JUMAIRAH VILLAGE L.L.C
Trust Account Number: 10549771830001
Account Trustee Name: ABU DHABI COMMERCIAL BANK

Pantheon Elysee Project Status

ACTIVE

Pantheon Elysee Project Status Detail

The project is registered in RERA for off plan sales and the records indicate that the project is under construction and was audited recently.

Pantheon Elysee Project Description

RESIDENTIAL AND COMMERCIAL (2B+G+4+R) WITH RETAILS AT GROUND FLOOR with internal and external finishes

Pantheon Elysee Inspection Notes

At the time of inspection the following were found: mobilization, enabling and foundation works substantially completed. Sub structure works progressing at advance stages. Superstructure works progressing with verticals at 3rd floor. Internal works progressing with block and plaster works at basement and ground floors.